Luis Esteban Valencia Muñoz

Hello I am using CMMi process template and it says that everything is unplanned work.

How can I make a workitem to count as planned work

And another question what is Triage I am from Medellin colombia and I didnt find a traslation to the word triage.

Thanks




Re: Team Foundation Server - Reporting & Warehouse How can I make tasks to be planned work?

Kathirvel

hi,

I could answer for your second question...Triage..this is actually a medical term which describes about the patient records which is grouped or classified into particular way...the same thing used in software industry ..especially in agile methodology ...we are using for the Team formation or group named "Triage" which means a group which will INVESTIGATE or APPROVE a bug which is reported by the Testing team...

when the Triage team apporved the bug after Investigation ...it will send to the developer to fix the bug...so the transitions here is for Triage team INVESTIGATE or APPROVED.

Hope this helps...

Thanks,

Kathir





Re: Team Foundation Server - Reporting & Warehouse How can I make tasks to be planned work?

Mauli Shah - MSFT

Hi Luis,

For the word triage, kathir has a good explanation. The idea behind triage is that the team does not have enough resources to fix every defect found. So they must figure out which are the more important, user-impacting defects. This process is called triage.

The way that the Unplanned Work report is calculated is that all work items filed after the date specified in "Plan Completion Date" parameter is considered to be 'unplanned'. You can change this parameter to include the work items that you want.

mauli





Re: Team Foundation Server - Reporting & Warehouse How can I make tasks to be planned work?

Kathirvel

Hi Luis,

Is my post about Triage and Mauli shah post about Task Plan are helpful to you...if not please let me know about your need. Please close this issue if you are done.

Thanks
Kathir